Question:

Can the constructor puts lean on the house that he hasn't finish the job

by  |  earlier

0 LIKES UnLike

Can the constructor puts lean on the house that he hasn't finish the job

 Tags:

   Report

1 ANSWERS


  1. If payments have not been made according to contract he can..he doesn't have to finish yet if payments aren't made on time as the contract says..unless you have a dispute on his billing or inferior construction