Can you list important checks before pouring, after pouring concrete in columns, beams and slab?

by  |  earlier

0 LIKES UnLike

Requesting for general checklist for reinforcement checking in beams, columns and slab

 Tags:

   Report

2 ANSWERS


  1. First, check the rebar to make sure it is in the proper location, proper size, and is supported to keep it in place during pour. Check location and dimensions of the pour. If you are pouring a column, make sure the concrete will be placed without a drop of more than 3 feet, use a trimmy if needed. Make sure they have the proper tools to place and finish the concrete, including trowels, floats, vibrators, etc. Finally, make sure and accessories or inbeds are in place and secured to prevent movement during pour.


  2. let me see, steel, right size of the hole , if you have any wiring to running in side that column or plumb pipe and make sure the box is straight with right height,. how come you don't have a permit or a blueprint of what you doing. let the concrete set for two days before taking down ply-board

Question Stats

Latest activity: earlier.
This question has 2 answers.

BECOME A GUIDE

Share your knowledge and help people by answering questions.