completing the project ?
(I was fascinated by the publication of the book "Collins Class Submarine Story: Steel, Spies and Spin" and searched and found this
on the net:
<<In August 1991, because of the combat system schedule slippage, the contract was amended to provide a two-stage delivery. This was to allow submarine platform trials to proceed in advance of a fully compliant combat system being available.
In September 1993, ASC notified sub-contractor Rockwell of a default in contract (non-delivery of the combat system), but were not allowed by Defence to proceed and instead the delivery method was further changed from two-stage to multiple increments, with increasing functionality and complexity to be introduced with each delivery.>>
http://www.defence.gov.au
/minister/1999/collins.html)
Perhaps the programming support environment available in the DT&E lab wasn't up to the job. But if so, what might have caused that ?
"What was sported with on the field of Causality
Was not there when the rules of the game were laid down;
It was thrown in today by way of pretext,
Tomorrow all will be as was set up before."
(The Ruba'iyat of Omar Khayyam -
by Omar Khayyam, translated by Peter Avery, John Francis Alexander Heath-Stubbs, John Heath-Stubbs, 1982, Penguin)
Tags: