Question:

How to find the interest between present and future value?

by  |  earlier

0 LIKES UnLike

Present Value

$400

Years

11

Future Value

$684

 Tags:

   Report

1 ANSWERS


  1. FV = PV * (1 + i)^n

    684 = 400 * (1 + i)^11

    684/400 = (1+i)^11

    log(684/400) = log( (1+i) ^ 11)

    log(684/400) = 11 * log (1 + i)

    log(684/400) / 11 = log (1+ i)

    10^((log(684/400))/11) = 10 ^ log (1+i)

    10^((log(684/400))/11) = 1 + i

    i = 10^((log(684/400))/11) - 1

    i = 10^0.021181465 - 1

    i = 1.04998 - 1

    i = 0.04998

    4.998 % / year