Question:

If 5 carpenters can make 30 tables in 2 days, how long will it take for 8 carpenters to make 100 tables?

by  |  earlier

0 LIKES UnLike

If 5 carpenters can make 30 tables in 2 days, how long will it take for 8 carpenters to make 100 tables?

 Tags:

   Report

3 ANSWERS


  1. You need to calculate the time it takes to make one table.

    You know that it takes 5X2 carpenter days to make 30, so 10/30 or 1/3 carpenter day per table.

    For 100 tables you require 33.3 carpenter days.  If 8 carpenters are working concurrently, then 33.3/8 = 4.16 days.


  2. So 5 carpenters make 15 tables in a day, or 3 each, on average.

    Therefore, 8 carpenters make 24 a day,

    so 100 will take 4.16 days

  3. I think it would take 12-1/2 days with 8 carpenters to make 100 tables.