Can someone please help me find the optimistic and pessimistic times? I am lost in what is the first step to take in finding critical path.The following represents a project with known activity times.ACTIVITY****IMMEDIATE PREDECESSOR***TIME(in weeks)A ****- **** 4B **** - **** 3C ****a**** 2D ****b**** 7E ***c.d*** 4F ****b**** 5G ***e,f *** 4