All Seasons, Inc. ordered $5,000 worth of Christmas decorations from Santa, Inc. The shipment of decorations was to arrive no later than October 1, in time for the Christmas season. The shipment did not arrive until December 1. In spite of the delay, All Seasons covered a third of the order through other suppliers, but had to pay 15% more than the price under contract with Santa, Inc. As a further result of the delay, All Seasons' sales were down 25%. All Seasons can recover:
A/punitive damages.
B/nominal damages.
C/compensatory damages and consequential damages.
D/compensatory damages, consequential damages, and punitive damages.
Tags: