Question:

What is timeline to repave parking lot?

by  |  earlier

0 LIKES UnLike

how long might it take to repave a 35 car parking lot...

ripping up old material/preparing ground/repave/harden

 Tags:

   Report

2 ANSWERS


  1. USA   The amount of work stated can be accomplished by a good reputable paving contractor in less than one week, start to finish.

    You might be dealing with a small contractor that does not have enough equipment or manpower to do the job quickly.  The contractor chosen might be a 3 or 4 person operation, that takes a long time to do the work but gets the job because they are cheap.

    Check with your local municipality for rental ordinances.  If you cannot use the parking, you might be entitled to a rent rebate.  The building owner should provide alternative parking.


  2. with weather on your side,,, 1 day to remove, 1 - 1 1/2 day(s) to prep, 1 day for base coat, 1 day for top coat, 1 day to cure, a few hours to stripe and 2 hours cure on paint  

Question Stats

Latest activity: earlier.
This question has 2 answers.